Highway Construction Inspection Performance Measures

Level I Performance Measures

0101-1101

Locate points on the work site based on information on project drawings.

0101-1102

Identify pertinent contract information provided in standards, specifications, plans, and special     provisions.

0101-1103

Perform arithmetic calculations, and calculate areas and volumes of simple geometric shapes,   including maintaining the correct precision.

0101-1104

Accurately measure dimensions and compare with values provided in applicable plans and   specifications.

0101-1105

Identify common tools and equipment used by inspectors for inspections, testing, and reporting on   the projects in which the candidate has been involved.

0101-1106

Identify common tools and equipment used in construction on the projects in which the candidate   has been involved.

0101-1107

Properly use personal protective equipment (PPE) appropriate for the construction site.

0101-1108

Identify specified work zone traffic control components.

0101-1109

Verify that specified erosion and sediment control components are in place.

0101-1110

Prepare concise, accurate, and understandable reports of daily activities.

Level II Performance Measures

0101-3101

Distinguish among types of soils and aggregates.

0101-3102

Inspect temporary erosion and sediment controls and stormwater management components for
compliance with project plans and specifications.

0101-3103

Inspect placement and grading of embankments, including compaction and finish tolerances, for
compliance with project specifications.

0101-3104

Inspect placement and grading of subgrades, undercuts, aggregate subbase and base courses, and
embankments, including compaction and finish tolerances, for compliance with project   specifications.

0101-3105

Inspect soil compaction methods and results and determine their acceptability according to project
specifications

0101-3106

Reliably conduct preplacement inspections before asphalt paving that correctly classify work items   as meeting specifications, not meeting specifications, or requiring further investigation.

0101-3107

Identify the sampling requirements for materials testing and verify compliance with project   specifications

0101-3108

Inspect delivery, placement, compaction, and finishing of asphalt for compliance with project
specifications.

0101-3109

Inspect surface preparation, forms, reinforcing steel, and load-transfer assemblies for concrete
pavements for compliance with project specifications.

0101-3110

Inspect delivery, testing, placement, and consolidation of concrete for pavement for compliance with
project specifications.

0101-3111

Inspect bedding for footings, and installation of footings and basic driven pile for compliance with
project specifications.

0101-3112

Inspect forms, reinforcing steel, delivery, and placement of concrete for structures for compliance   with project specifications.

0101-3113

Inspect bedding, backfilling, and installation of drainage components for compliance with project
specifications.

0101-3114

Inspect installation of drainage components for compliance with project specifications.

0101-3115

Inspect signage, striping, and message marking for compliance with project specifications.

0101-3116

Inspect guardrails, safety systems, and fencing for compliance with project specifications.

0101-3117

Inspect basic foundations for lighting, traffic signals, ground-mounted signs, and sound walls for
compliance with project specifications.

0101-3118

Inspect underground electrical conduit for compliance with project specifications.

0101-3119

Inspect sidewalks, curbs and gutters, curb ramps, medians/median barriers, and driveways for
compliance with project specifications.

0101-3120

Inspect environmental mitigation for compliance with project specifications.

0101-3121

Verify that the correct work zone traffic controls for lane shifts, closures, detours, and construction   access points and routes have been placed in accordance with project specifications.

0101-3122

Prepare, compile, and maintain project documentation related to work within the inspector’s scope of
responsibility.

0101-3123

Identify dates of project activities from a basic project schedule.

0101-3124

Communicate concerns about acceptability of work and other potential problems to the proper   contractor, engineering, and/or owner representatives in an accurate, professional, and timely
manner.

Level III Performance Measures

0101-5101

Inspect steep slopes and slope stabilization, both temporary and permanent.

0101-5102

Inspect support of excavations.

0101-5103

Inspect the installation of permanent geosynthetics and geogrids.

0101-5104

Inspect reinforced earth and mechanically stabilized embankments and walls.

0101-5105

Inspect grade tie-ins, drainage, elevations, and transitions on a multi-phase project.

0101-5106

Verify proper acceptance testing for water, sanitary, and storm sewer lines.

0101-5107

Identify dangers or potential problems in the work zone traffic flow.

0101-5108

Inspect drilled shafts or caissons.

0101-5109

Inspect steel structural components.

0101-5110

Inspect the erection of structural steel.

0101-5111

Verify the size, type, and tensioning of bolted structural steel connections.

0101-5112

Verify the size, type, and proper composition of welded structural steel connections.

0101-5113

Inspect the handling and erection of pre-stressed concrete I-beams or box beams.

0101-5114

Inspect bridge deck construction, including pre-pour inspection.

0101-5115

Inspect the application of paint and coatings.

0101-5116

Inspect the erection of structures for signals, signage, and lighting.

0101-5117

Inspect the installation of components and wiring for lighting and verify functionality.

0101-5118

Review inspection reports from staff for completeness and content, and report work, including minor   field modifications, results, non-conformances, and actions taken.

0101-5119

Prioritize and coordinate inspection activities of available inspection personnel.

0101-5120

Inspect project activities for general conformance with OSHA safety requirements.

0101-5121

Prepare, compile, organize, and maintain accurate project documentation for all activities within the   inspector’s scope of responsibility.

Level IV Performance Measures

0101-7101

Identify critical construction activities, based upon their impacts on safety, the project schedule, or   the public.

0101-7102

Identify, and verify conformance with, hold-points for critical and complex inspections.

0101-7103

Develop project inspection plans.

0101-7104

Identify, diagnose, and respond to unforeseen factors or events, initiating plans of action that   minimize delays.

0101-7105

Verify that the project schedule conforms with the project scope and specifications.

0101-7106

Verify that schedule updates match the work completed to date and the work remaining.

0101-7107

Identify schedule conflicts.

0101-7108

Verify that work completed satisfies contract requirements for payment.

0101-7109

Accurately estimate remaining inspection and testing costs based on remaining construction work.

0101-7110

Identify plan errors and omissions and changed conditions in advance of construction.

0101-7111

Identify ambiguities or conflicts in project documents in advance of construction.

0101-7112

Identify the qualifications required for project inspections and testing and assess whether individuals   meet them.

0101-7113

Recognize appropriate contract modifications; prepare a rationale that justifies each change as   conforming with the owner’s requirements; and manage the change order process.

0101-7114

Calculate price adjustments required by the contract.

0101-7115

Verify that project wage rates comply with prevailing wage requirements.

0101-7116

Verify that project DBE and SBE work is in conformance with requirements for commercially useful   functions.

0101-7117

Manage a project’s final inspection, acceptance, and closeout to meet contract requirements.

0101-7118

Maintain effective communications and relationships with coworkers, contractors, and other   stakeholders.

0101-7119

Prepare, compile, organize, and maintain accurate and complete project documentation for all   activities within the inspector’s scope of responsibility.